7.8 Vertical Detecting Device
Ⅰ General Items
7.8.1 The connection direction of sprocket case,plug valve and rod tube shall meet the requirements in the design documents.
Check quantity:full check.
Check method:observe and check according to drawings.
7.8.2 The allowable installation deviation of vertical detecting device shall meet the requirements in Table 7.8.2.
Check quantity:full check.
Check method:see Table 7.8.2.
Table 7.8.2 Allowable installation deviation of vertical detecting device(mm)